Work item |
Material costs |
Labor costs |
formwork & scaffolding |
473 701 HUF |
517 618 HUF |
eatrh-work | - | 144 830 HUF |
groundwork | 446 637 HUF | 103 010 HUF |
concrete & reinforced concrete works | 1 218 682 HUF | 518 959 HUF |
masonry | 1 070 394 HUF | 977 148 HUF |
timber-work | 1 143 750 HUF | 1 703 208 HUF |
plastering | 324 930 HUF | 776 048 HUF |
roof-works | 180 242 HUF | 80 070 HUF |
facing | 529 261 HUF | 447 748 HUF |
tinning | 603 725 HUF | 535 930 HUF |
joinery | 3 884 597 HUF | 882 484 HUF |
339 611 HUF | 530 810 HUF | |
insulation | 3 455 586 HUF | 849 062 HUF |
paving | 283 142 HUF | 142 308 HUF |
water supply & drainage | 759 000 HUF | 894 000 HUF |
subsurface air transporting drainage | 567 000 HUF | 168 000 HUF |
Drexler-Weiss HHVAC installations | 3 939 000 HUF | 433 000 HUF |
HHVAC | 1 246 000 HUF | 1 124 000 HUF |
TOTAL | 20 465 356 HUF | 10 828 232 HUF |
material and labor costs TOTAL |
31 293 558 HUF
|
The estimation is informative and is not include VAT.