item | quantity | unit | material unit costs | labor unit costs | material TOTAL | labor TOTAL |
Walling: 30x25x23,8 cm POROTHERM (interlocking vertical joints) blocks with cement-lime mortar |
167 | m2 | 4 500 HUF | 4 284 HUF | 751 500 HUF | 715 428 HUF |
Walling: 25x25x23,8 cm POROTHERM (interlocking vertical joints) blocks with cement-lime mortar | 39,5 | m2 |
4 580 HUF |
2 800 HUF | 181 093 HUF | 110 712 HUF |
Partition wall: 10x50x23,8 cm POROTHERM (interlocking vertical joints) blocks with cement-lime mortar | 52 | m2 | 2 650 HUF | 2 904 HUF | 137 800 HUF | 151 008 HUF |
TOTAL | 1 070 393 HUF | 977 148 HUF |
The prices are informative.