item | quantity | unit | material unit costs | labor unit costs | material TOTAL | labor TOTAL |
concrete steel construction | 3,5 | t | 204 635 HUF | 90 000 HUF | 716 222 HUF | 315 000 HUF |
coloumn, pillar from reinforced concrete | 0,36 | m3 | 19 108 HUF | 5 200 HUF | 6 879 HUF | 1 872 HUF |
reinforced concrete beam | 0,5 | m3 | 19 108 HUF | 4 500 HUF | 9 363 HUF | 2 205 HUF |
reinforced concrete ring beam | 3,9 | m3 | 19 108 HUF | 5 200 HUF | 74 521 HUF | 20 280 HUF |
flat or ribbed reinforced concrete slab | 13,3 | m3 | 19 108 HUF | 5 200 HUF | 253 945 HUF | 69 108 HUF |
staircase | 1,4 | m3 | 19 108 HUF | 6 000 HUF | 26 752 HUF | 8 400 HUF |
floor slab from gravel concrete up to 6 cm | 7,1 | m3 | 18 517 HUF | 14 420 HUF | 131 000 HUF | 102 094 HUF |
TOTAL | 1 218 682 HUF | 518 959 HUF |
The prices are informative.